First Annual Block Party & Public Tour

March 2, 2017

12 Month Performance Period Begins

January, 2017

Open for Business

January 3, 2017

Move-In!

December 30, 2016

Temporary Certificate of Occupancy

December 30, 2016

Composting System Training

December 30, 2016

Lay-In Ceilings Complete

December 30, 2016

Network Backbone Complete

December 29, 2016

New Freestanding Furniture Installed

December 28, 2016

Reused Systems Furniture Installed

December 27, 2016

Car Charging Station Installed

December 27, 2016

Composting System Operational

December 27, 2016

Monodraught Suncatchers Terminated

December 26, 2016

Rainwater-to-Potable System Ready

December 23, 2016

Gray Water System Operational

December 23, 2016

HVAC Test & Balance Complete

December 23, 2016

Offsite Paving Complete

December 19, 2016

Public Art Bike Rack Installed

December 19, 2016

Carpet Installed

December 19, 2016

Sheetrock Complete

December 18, 2016

Signage Permit Issued

December 16, 2016

Canopy Photovoltaic Panels Installed

December 16, 2016

Cisterns Leak Tested

December 15, 2016

Photovoltaic Canopy Erected

December 15, 2016

Photovoltaic Permit Issued

December 15, 2016

Electric Room Sign-Off

December 13, 2016

Ceramic Tile Complete

December 9, 2016

Composting Units Installed

December 2, 2016

Cisterns Installed

November 30, 2016

VRF Units Installed

November 29, 2016

Roof Complete

November 22, 2016

Solatubes Installed

November 22, 2016

Cistern Bathtub Poured

November 11, 2016

Interior Framing Complete

November 10, 2016

Alley Repaved

November 9, 2016

Underside of Deck Painted

November 4, 2016

One-Side Sheetrock Complete

October 28, 2016

In-Wall Rough-In Complete

October 18, 2016

Public Art Bike Rack Permit Issued

October 6, 2016

Interior Underground Plumbing Complete

September 16, 2016

Helical Piers Installed

September 9, 2016

Helical Pier Permit Issued

August 25, 2016

LEED Design Final Approval

August 16, 2016

Corner Steel Erected

August 8, 2016

Offsite Permit Issued

July 29, 2016

Leachate Tank Placed

July 21, 2016

Natural Gas Line Abandoned

June 13, 2016

LEED Design Preliminary Submittal

April 28, 2016

Renovation Begins

April 22, 2016

Building Permit Issued

April 22, 2016

Deconstruction Begins

March 9, 2016

Deconstruction Permit Issued

March 9, 2016

Construction Documents Completed

December 21, 2015

Community Engagement Event #2

October 10, 2015

930 R Street Property Purchased

September 15, 2015

Community Engagement Event #1

August 10, 2015

LEED v4.0 Project Registration

July 17, 2015

Living Building Challenge v3.0 Project Registration

July 17, 2015

Biophilia Workshop

July 10, 2015

Seattle Precedent Trip

July 6, 2015

Design Team Selected

June 15, 2015

930 R Street Property Targeted

June 1, 2015

Property Search Begins

May 27, 2015

Project Conceived

May 1, 2015