LBC Performance Period Begins

October 1, 2021

LBC Ready Status Achieved

September 29, 2021

LBC Ready Audit Submitted

August 3, 2021

First Month of Net Positive Energy Achieved

JULY 31, 2021

GREYWATER SYSTEM OPERATIONAL

JUNE 24, 2021

MOVE-IN COMPLETE

JUNE 17, 2021

TEMPORARY CERTIFICATE OF OCCUPANCY OBTAINED

JUNE 10, 2021

SYSTEMS FURNITURE INSTALL COMPLETE

JUNE 3, 2021

METAL CLADDING ON LOBBY MEDIA WALL INSTALLED

MAY 27, 2021

COURTYARD FOLDING GLASS DOORS INSTALLED

MAY 20, 2021

CAFE CEILING PAINTED (BLUE!)

MAY 13, 2021

LIVING WALL TROUGHS INSTALLED

MAY 6, 2021

CONCRETE FLOOR POLISHING COMPLETE

ARPIL 29, 2021

CONCRETE FLOOR POLISHING COMPLETE

ARPIL 29, 2021

DEMOUNTABLE PARTITION INSTALLATION BEGINS

ARPIL 22, 2021

CARPET INSTALLATION BEGINS

ARPIL 15, 2021

SEWER METER MANHOLE INSTALLED

ARPIL 8, 2021

CANOPY STEEL DELIVERED

ARPIL 1, 2021

CISTERN PAD POURED

MARCH 18, 2021

LIVING WALLS WATERPROOFED

MARCH 11, 2021

EXISTING CONCRETE DOUBLE-TEE ROOF DECONSTRUCTED AT NEW COURTYARD

MARCH 4, 2021

MICRO PILES FOR SOLAR PV CANOPIES COMPLETE

FEBRUARY 18, 2021

ELEVATOR PIT POURED

FEBRUARY 11, 2021

INFILTRATION WELL CONSTRUCTED

FEBRUARY 4, 2021

DEMOLITION FOR NEW WINDOWS COMPLETE

JANUARY 28, 2021

PHANTOM BUS SHELTER PUBLIC ART DESIGN COMPETITION WINNER ANNOUNCED

JANUARY 25, 2021

INTERIOR STEEL STUD FRAMING BEGINS

JANUARY 21, 2021

SOLAR PHOTOVOLTAIC PARKING CANOPY FOOTINGS BEGIN

JANUARY 14, 2021

RESTROOM CONCRETE FLOORS RE-POURED

JANUARY 7, 2021

PHANTOM BUS SHELTER PUBLIC ART DESIGN COMPETITION LAUNCHED

JANUARY 4, 2021

PROJECT WEBSITE PUBLISHED

JANUARY 4, 2021

ELECTRICAL TRENCHES COMPLETE

DECEMBER 30, 2020

EXISITING CONCRETE BLOCK AT NEW OPENINGS GROUTED

DECEMBER 23, 2020

CURB CONSTRUCTION FOR NEW SOLATUBE SKYLIGHTS BEGINS

DECEMBER 17, 2020

UNDER-SLAB PLUMBING BEGINS

DECEMBER 10, 2020

SYSTEMS FURNITURE & DEMOUNTABLE PARTITIONS SELECTED

DECEMBER 1, 2020

PHANTOM BUS SHELTER PUBLIC ART RFQ PUBLISHED

NOVEMBER 30, 2020

EXISTING CONDUIT BANK AT EXISTING COURYARD DECONSTRUCTED

NOVEMBER 25, 2020

BUILDING PERMIT ISSUED

NOVEMBER 25, 2020

NEW COURTYARD EXCAVATION BEGINS

NOVEMBER 19, 2020

SAWCUTTING FOR LIVING WALLS AND NEW COURTYARDS BEGINS

NOVEMBER 12, 2020

GAS FIRED WATER HEATERS REMOVED

November 5, 2020

CONSTRUCTION FENCING & SIGNAGE INSTALLED

NOVEMBER 5, 2020

SELECTIVE DECONSTRUCTION BEGINS

OCTOBER 19, 2020

BID AWARDED

OCTOBER 7, 2020

CONSTRUCTION DOCUMENTS COMPLETED

AUGUST 20, 2020

CONSTRUCTION DOCUMENTS

SUMMER 2020

LBC V4.0 PROJECT REGISTRATION (AFFORDABLE NET POSITIVE WATER SOLUTION FOUND!)

MARCH 20, 2020

DESIGN DEVELOPMENT

WINTER & SPRING 2020

SCHEMATIC DESIGN

FALL & WINTER 2019

BIOPHILIA WORKSHOP

JULY 10, 2019 (4 YEARS TO THE DAY FROM AN SAC’S CHARRETTE!)

DESIGN TEAM SELECTED

MAY 22, 2019

REGENERATIVE PROJECT CONCEIVED

MAY 11, 2019

LEED-EB V4.0 PLATINUM RECERTIFIED

WINTER 2019   

LEED-EB V3.0 PLATINUM CERTIFIED

WINTER 2014   

ENERGY STAR CERTIFIED

WINTER 2012

LEED-NC V3.0 PLATINUM CERTIFIED

SPRING 2011

ORIGINAL MOVE-IN!

SPRING 2010

BUILDING PERMIT ISSUED

FALL 2009

2505 PARLEYS WAY PROPERTY TARGETED

SUMMER 2009

PROPERTY SEARCH

SPRING 2009

SUSTAINABLE PROJECT CONCIEVED

FALL 2008